Find here details of SA213 Seamless Steel Pipe on our website. Today we would like to talk about the process of seamless steel pipe.


The production process of general seamless steel pipe can be divided into cold drawing and hot rolling. The production process of cold rolled seamless steel pipe is generally more complicated than hot rolling. The pipe blank must first be rolled in three rolls. Sizing test, if the surface does not respond to the crack, the round tube is cut by a cutter and cut into a blank of about one meter in length. Then enter the annealing process, the acidification should be acid washed with acid liquid, pickling should pay attention to whether there is a lot of foaming on the surface, if there is a lot of foaming, the quality of the steel pipe can not meet the response standard. The appearance of cold-rolled seamless steel pipe is shorter than that of hot-rolled seamless steel pipe. The wall thickness of cold-rolled seamless steel pipe is generally smaller than that of hot-rolled seamless steel pipe, but the surface looks brighter than thick-walled seamless steel pipe, and the surface is not too It's rough and there aren't too many burrs in the caliber. 


SA213 Seamless Steel Pipe

SA213 Seamless Steel Pipe


As a X42 Seamless Steel Pipe Factory, we know that the delivery status of the hot-rolled seamless steel pipe is generally delivered after the heat treatment in the hot rolled state. After the quality inspection, the hot-rolled seamless steel pipe is subjected to strict manual selection by the staff. After the quality inspection, the surface is oiled, followed by multiple cold drawing experiments, and the perforation experiment is performed after the hot rolling treatment. If the perforation is too large, straightening correction is required. After straightening, the conveyor is sent to the flaw detector for flaw detection experiments, and finally labeled, formatted, and placed in the warehouse.


Round tube billet → heating → perforation → three-roll cross-rolling, continuous rolling or extrusion → pipe removal → sizing (or reducing diameter) → cooling → straightening → hydraulic test (or flaw detection) → marking → storage seamless steel pipe The steel tube or the solid tube blank is made into a capillary tube by perforation, and then is formed by hot rolling, cold rolling or cold drawing. The specifications of the seamless steel pipe are expressed by the outer diameter * wall thickness in millimeters. Seamless steel tubes are divided into two types: hot rolled and cold rolled (dial) seamless steel tubes. Hot-rolled seamless steel pipes are divided into general steel pipes, low and medium pressure boiler steel pipes, high pressure boiler steel pipes, alloy steel pipes, stainless steel pipes, petroleum cracking pipes, geological steel pipes and other steel pipes. Cold-rolled (dial) seamless steel pipe is divided into general steel pipe, low and medium pressure boiler steel pipe, high pressure boiler steel pipe, alloy steel pipe, stainless steel pipe, petroleum cracking pipe, other steel pipes, and also includes carbon thin-walled steel pipe and alloy thin-walled steel pipe. Stainless steel thin-walled steel pipe and special-shaped steel pipe. The outer diameter of hot-rolled seamless pipe is generally larger than 32mm, the wall thickness is 2.5-200mm, the diameter of cold-rolled seamless steel pipe can reach 6mm, the wall thickness can reach 0.25mm, the outer diameter of thin-walled pipe can reach 5mm, the wall thickness is less than 0.25mm, cold Rolling is more accurate than hot rolling.


Generally, the seamless steel pipe is formed by hot-rolled or cold-rolled low-alloy structural steels such as 10, 20, 30, 35, 45 and other high-quality carbon steels such as 16Mn and 5MnV or 40Cr, 30CrMnSi, 45Mn2, and 40MnB. Seamless pipes made of low carbon steel such as 10 and 20 are mainly used for fluid conveying pipes. 45, 40Cr and other medium carbon steel seamless pipes are used to make mechanical parts, such as the force parts of automobiles and tractors. Generally, seamless steel pipes are required to ensure strength and flattening test. The hot rolled steel pipe is delivered in a hot rolled state or a heat treated state; the cold rolling is delivered in a heat treated state by heat.


We also have ERW Steel Pipes. If you need any information about it, feel free to contact us.


*
*
*
*
*